Weddin Shire Council

ROADWORKS

Weddin Shire Council proposes to carry out road works on the Mid-Western Highway at the Greenethorpe Bumbaldry Road intersection with preliminary survey works to commence on the 25th February. The works involve the clearing of land for sight distance purposes followed by drainage structure widening and then intersection widening to allow for the safe movement of heavy vehicles .Council expects that roadworks will be completed by the 30th June 2019 with speed restrictions and traffic control in place for the duration of the work. The works are subject to satisfactory weather conditions. Working hours will be between 7am and 6pm.

 

Possible delays may be experienced during the road works. Council apologises for any inconvenience and will endeavour to act as promptly as possible, shall you need access to property gates throughout the worksite.

 

Please contact Phil on 0439 980 098 or Shahab on 0417 808 276, if you have any queries.